Charing Cross Hospital – 8th Floor, MDT, Refurbishment
Healthcare Charing Cross Hospital – 8th Floor, MDT, Refurbishment Budget: £190,000
Client: NHS

The project undertaken was for the refurbishment of the existing MDT Room on the 8th Floor at Charing Cross Hospital. Works completed included the strip-out of the existing area; complete refurbishment consisting of new vinyl & carpet flooring, suspended grid ceilings, Audio & Visual systems, fitted furniture and full decoration of the associated area. Furthermore the existing Mechanical plant and ventilation ductwork was upgraded, BMS integration, including a full rewire of the electrical cabling, new sub-mains cabling from Ground Level, installation of new Distribution boards and P4 emergency lighting. The project revolved around the management of two MDT rooms on separate sites concurrently, all completed within a 8 week programme.